Completed Projects - 2018


National Bank of Egypt (Archive Room)

 

Location

Cairo

Year Completed

2018

System Installed

- FM200 System

- Fire Alarm Ctrl. System

Owner

National Bank of Egypt

Main Contractor

Unisafe

Consultant

Arcmid Consultant Engineering

 

Cairo Intel. Convention Centre Halls Rehabilitation - Contract 22/2015/2016

 

Location

Cairo

Year Completed

2018

System Installed

- FM200 System

- CO2 System

Owner

Ministry of Trade and Industry

Main Contractor

Arab Contractors

Consultant

Diaa Consult

 

Alexandria Carbon Black Co.

 

Location

Alexandria

Year Completed

2018

System Installed

- FM200 System

- Fire Alarm & ctrl System

Owner

Alexandria Carbon Black Co. (Aditya Birla)

Main Contractor

UNISAFE

Consultant

MAS Engineering Consultant